Actual exam question for APM's APM-PFQ exam
Question #: 18
Topic #: 6
[All APM-PFQ Questions]

Which one of the following statements is true?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Pamella
2 days ago
Hmm, I'm not sure. A and D also seem plausible. This is a tricky one!
upvoted 0 times
...
Denny
8 days ago
I think the correct answer is C. Quality control is all about verifying that the project deliverables meet the specified requirements.
upvoted 0 times
...
Lavera
20 days ago
But A makes sense because quality assurance is about ensuring the project manager delivers on time and to budget.
upvoted 0 times
...
Nettie
22 days ago
I disagree, I believe it's C.
upvoted 0 times
...
Lavera
24 days ago
I think the true statement is A.
upvoted 0 times
...