APM Exam APM-PFQ Topic 4 Question 24 Discussion

Actual exam question for APM's APM-PFQ exam
Question #: 24
Topic #: 4
[All APM-PFQ Questions]

Which structure shows the reporting relationships and communications channels for a project?

Show Suggested Answer Hide Answer
Suggested Answer: A, A

Contribute your Thoughts:

Dalene
4 days ago
What, no 'All of the above' option? That's the answer I was going to pick!
upvoted 0 times
...
Magdalene
5 days ago
Hmm, I thought the Responsibility assignment structure would be the answer. Guess I need to review my project management knowledge a bit more.
upvoted 0 times
...
Nelida
10 days ago
I'm going with B as well. The OBS is the best tool to visualize the reporting relationships on a project.
upvoted 0 times
...
Noe
11 days ago
Hmm, I see your point. But I still think B) Organisational Breakdown Structure makes more sense.
upvoted 0 times
...
Stephaine
12 days ago
I disagree, I believe the correct answer is D) Responsibility assignment structure.
upvoted 0 times
...
Beckie
17 days ago
The Organisational Breakdown Structure seems like the obvious choice here. That shows the hierarchy and communication channels within the project team.
upvoted 0 times
Patria
3 days ago
I agree, the Organisational Breakdown Structure is the best option for showing reporting relationships.
upvoted 0 times
...
...
Noe
22 days ago
I think the answer is B) Organisational Breakdown Structure.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77