Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APM Exam APM-PFQ Topic 2 Question 16 Discussion

Actual exam question for APM's APM-PFQ exam
Question #: 16
Topic #: 2
[All APM-PFQ Questions]

A member of your team has described being involved in a risk event. Which one of the following would best describe such an event?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Kent
28 days ago
Option C is the clear winner here. Unless, of course, the correct answer is a risk event that involves unicorns and rainbows. Then I'm changing my vote!
upvoted 0 times
...
Lucille
30 days ago
C is the way to go. Although I'm tempted to choose D just to see a 'risk identification workshop' in action. Sounds like fun!
upvoted 0 times
...
Candida
1 months ago
This is a tricky one, but I'm going with C. A risk event is an uncertain event, not an action plan or a workshop.
upvoted 0 times
...
Von
1 months ago
I was a bit unsure at first, but after reading the options, I think C is the best answer. It's the only one that accurately describes a risk event.
upvoted 0 times
Kanisha
1 days ago
I agree, option C is the most accurate description of a risk event.
upvoted 0 times
...
...
Kaitlyn
1 months ago
Option C definitely seems to be the correct answer here. A risk event is an uncertain event or set of circumstances that, if realized, would have an effect on project objectives.
upvoted 0 times
A: I agree, option C is the best description of a risk event.
upvoted 0 times
...
...
Amalia
2 months ago
I think option A) also makes sense, as it involves taking actions to reduce the impact of a threat.
upvoted 0 times
...
Edna
2 months ago
I agree with Janae. A risk event is definitely something that could impact project objectives.
upvoted 0 times
...
Janae
2 months ago
I think the best description would be C) An uncertain event or set of circumstances that would affect project objectives.
upvoted 0 times
...

Save Cancel