APICS Exam CPIM Topic 3 Question 81 Discussion

Actual exam question for APICS's Certified in Production and Inventory Management exam
Question #: 81
Topic #: 3
[All Certified in Production and Inventory Management Questions]

The percentage of time that the work center is active compared to the available time is called:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Emilio
1 days ago
I agree with Ciara, work center utilization measures how much time is spent working.
upvoted 0 times
...
Ciara
2 days ago
I think the answer is A) Work center utilization.
upvoted 0 times
...