If the run time per piece on operation B is shorter than that on A, the first batch must be larger enough to avoid idle time on operation A

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Oliva
1 days ago
I disagree, I believe it's false. Just because B is faster doesn't mean we need a larger batch for A. It depends on the overall process flow.
upvoted 0 times
...
Antione
2 days ago
I think the statement is true because if operation B is faster, we need to make sure operation A doesn't have any idle time.
upvoted 0 times
...
Shay
15 days ago
Yes, that's correct. It prevents idle time on operation A.
upvoted 0 times
...
Annelle
16 days ago
So you agree that the first batch must be larger if operation B is faster?
upvoted 0 times
...
Shay
17 days ago
True
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77