APICS Exam CPIM Topic 1 Question 71 Discussion

Actual exam question for APICS's CPIM exam
Question #: 71
Topic #: 1
[All CPIM Questions]

Any changes can be made to the MPS as long as it is within the limits set by the production plan. Changes are routine and are often made by the computer program. This is the scenario in zone of time fence.

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Keena
2 days ago
I'm going with D) None of these. The question doesn't seem to be describing any of the given options.
upvoted 0 times
...
Yuette
7 days ago
I'm not sure about this one. I think it could also be A) Slushy Zone because changes can be a bit flexible sometimes.
upvoted 0 times
...
Lynda
8 days ago
I agree with Sharen. Changes within the limits set by the production plan are usually made in the Liquid Zone.
upvoted 0 times
...
Sharen
12 days ago
I think the answer is C) Liquid Zone.
upvoted 0 times
...
Coral
13 days ago
I'm not sure, but I think it could also be A) Slushy Zone because changes are routine and often made by the computer program.
upvoted 0 times
...
Paris
14 days ago
Hmm, I think the answer is B) Frozen Zone. Changes to the MPS are limited in this zone, not routine as mentioned in the question.
upvoted 0 times
...
Corrie
16 days ago
I agree with Brock, changes within the limits set by the production plan are usually made in the Liquid Zone.
upvoted 0 times
...
Brock
21 days ago
I think the answer is C) Liquid Zone.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77