Which of the following statements is true about items that appear on a final assembly schedule?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Renato
8 days ago
This question is so straightforward, it's making me hungry. I wonder if the final assembly schedule includes snacks?
upvoted 0 times
...
Lashawn
20 days ago
A? Really? That's like saying the cake doesn't appear on the recipe. Of course they're on the shipment schedule!
upvoted 0 times
...
Eric
22 days ago
C seems tempting, but I doubt they'd just release stuff without considering the components. That would be a logistical nightmare!
upvoted 0 times
Cherry
14 hours ago
C) They are released without regard for component availability.
upvoted 0 times
...
Royal
6 days ago
B) They are stated in terms of end items or customer orders.
upvoted 0 times
...
Galen
11 days ago
A) They do not appear on a shipment schedule.
upvoted 0 times
...
...
Nguyet
29 days ago
Hmm, I'd go with D. The final assembly schedule is vital for the production plan, right? It's like the roadmap for the whole operation.
upvoted 0 times
Pearlie
5 days ago
I agree, it's like the blueprint for how everything comes together in production.
upvoted 0 times
...
Simona
13 days ago
Yes, you're right. The final assembly schedule is definitely used as input to the production plan.
upvoted 0 times
...
...
Alishia
1 months ago
I'm pretty sure it's option B. The final assembly schedule is all about end items and customer orders, not random parts.
upvoted 0 times
...
Josefa
1 months ago
I'm not sure, but I think D) They are used as input to the production plan makes sense too.
upvoted 0 times
...
Carin
1 months ago
I agree with Lavera, because final assembly schedule items are usually related to end products.
upvoted 0 times
...
Lavera
1 months ago
I think the answer is B) They are stated in terms of end items or customer orders.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77
a