APICS Exam CPIM-MPR Topic 2 Question 108 Discussion

Actual exam question for APICS's CPIM-MPR exam
Question #: 108
Topic #: 2
[All CPIM-MPR Questions]

The following question is based on the following information:

The master production schedule quantity that should be placed in Period 7 is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Arlene
10 days ago
Hmm, let me think about this. The image shows the Master Production Schedule, and we need to determine the quantity for Period 7. Based on the data, I'd say the correct answer is C) 13.
upvoted 0 times
...
Kindra
13 days ago
I'm not sure, but I think D) 20 could also be a possible answer.
upvoted 0 times
...
Lindsey
14 days ago
I agree with Daniela, C) 13 seems to be the right choice based on the information provided.
upvoted 0 times
...
Daniela
22 days ago
I think the answer is C) 13.
upvoted 0 times
...