Scenario

You are a newly hired planner involved in the process of preparing a new recreation plan for your community. Your supervisor learns that the City Council is anxious to take action on a recreation plan, and therefore, you are instructed to prepare the plan without scheduling any time for public participation or public comment. What might you do first?

Show Suggested Answer Hide Answer
Suggested Answer: A

B . wrote Edge Cities in 1991

C . wrote Making City Planning Work in 1985

D . advocate for new urbanism or neotraditional design


Contribute your Thoughts:

Herminia
1 months ago
Public participation? That's like asking a cat to do the chicken dance. It's just not gonna happen. I better get creative and find a way to sneak in some citizen input without the supervisor catching on.
upvoted 0 times
...
Angella
2 months ago
Haha, skip public participation? Good luck with that one. The citizens are gonna revolt and storm City Hall with pitchforks if you try that. Time to put on my negotiation hat and convince the supervisor to do this the right way.
upvoted 0 times
Reuben
15 days ago
B) The first step is to be sure you understand the situation completely, and, most importantly, you must know if public participation required by law. You know that as a planner, your responsibility is to provide full.
upvoted 0 times
...
Gearldine
1 months ago
Haha, skip public participation? Good luck with that one. The citizens are gonna revolt and storm City Hall with pitchforks if you try that. Time to put on my negotiation hat and convince the supervisor to do this the right way.
upvoted 0 times
...
Ressie
1 months ago
A) The first step is to be sure you understand the situation completely, and, most importantly, you must know if public participation required by law. You know that as a planner, your responsibility is to provide full, clear and accurate information on planning issues to citizens and governmental decision-makers and to strive to give citizens the opportunity for meaningful impact on the development of plans (Ethical Principle 1)
upvoted 0 times
...
...
Patria
2 months ago
Whoa, hold up! No public input? That's a recipe for disaster. I better double-check the legal requirements before I do anything else. This could be a real career-breaker if I mess it up.
upvoted 0 times
Catarina
4 days ago
B) Whoa, you're right. No public input could lead to some serious consequences. It's crucial to follow the legal requirements and ensure that the community has a voice in the decision-making process.
upvoted 0 times
...
King
14 days ago
A) The first step is to be sure you understand the situation completely, and, most importantly, you must know if public participation required by law. You know that as a planner, your responsibility is to provide full, clear and accurate information on planning issues to citizens and governmental decision-makers and to strive to give citizens the opportunity for meaningful impact on the development of plans (Ethical Principle 1)
upvoted 0 times
...
...
Merri
2 months ago
I can't believe the supervisor wants to skip public participation! That's like planning a wedding without the bride and groom. The public deserves a voice, even if the City Council is in a hurry.
upvoted 0 times
Loreta
1 months ago
B) I agree, public participation is crucial in the planning process. It's important to ensure that all stakeholders have a voice in the decision-making process.
upvoted 0 times
...
Diego
2 months ago
A) The first step is to be sure you understand the situation completely, and, most importantly, you must know if public participation required by law. You know that as a planner, your responsibility is to provide full, clear and accurate information on planning issues to citizens and governmental decision-makers and to strive to give citizens the opportunity for meaningful impact on the development of plans (Ethical Principle 1)
upvoted 0 times
...
...
Fabiola
2 months ago
Definitely, we need to make sure we understand the situation completely before taking any action.
upvoted 0 times
...
Heidy
2 months ago
I think it's important to follow the ethical principle of providing citizens with the opportunity for meaningful impact on planning issues.
upvoted 0 times
...
Fabiola
2 months ago
I can't believe we're not allowed to schedule any time for public participation in the recreation plan.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77