A designer notices that no tasks associated with a specific project appear on their timesheet. The project owner verified that the designer is assigned to several tasks and that the tasks occur during the week of the current timesheet
Which setting can cause this experience?
Project status and timesheets:
For tasks to appear on a timesheet, the project status must be set to 'Current.' If the project status is anything other than Current (e.g., Planning, Complete, or On Hold), tasks from that project will not automatically populate the timesheet.