What does the Cost Performance Index (CPI) of a project in Workfront track?

Show Suggested Answer Hide Answer
Suggested Answer: A

The CPI measures the cost efficiency of budgeted resources on a project. It is calculated by dividing the earned value (EV) by the actual cost (AC). A CPI value greater than 1 indicates that the project is under budget.


Contribute your Thoughts:

Daniel
10 months ago
I agree, it's important to monitor CPI to ensure project cost efficiency
upvoted 0 times
...
Sheldon
10 months ago
That makes sense, CPI helps us understand if we are under or over budget
upvoted 0 times
...
Noemi
10 months ago
I think it tracks the relationship between the planned and actual cost
upvoted 0 times
...
Aja
10 months ago
A) Relationship between the planned and actual cost
upvoted 0 times
...
Chaya
10 months ago
Wait, the CPI tracks the actual cost of a project? Clearly, someone needs to spend more time on Workfront! *chuckles*
upvoted 0 times
Antonio
9 months ago
Oh, I see. So it's all about comparing what was planned with what actually happened. Interesting!
upvoted 0 times
...
Lina
9 months ago
Yes, the Cost Performance Index (CPI) tracks the relationship between the planned and actual cost.
upvoted 0 times
...
Bo
9 months ago
C) Total expected value after calculating its benefit and removing the costs
upvoted 0 times
...
Dortha
9 months ago
A) Relationship between the planned and actual cost
upvoted 0 times
...
...
Roy
10 months ago
C) Total expected value after calculating its benefit and removing the costs. Gotta love that bottom line! The CPI is the perfect tool for keeping an eye on it.
upvoted 0 times
Carman
10 months ago
C) Total expected value after calculating its benefit and removing the costs. It's crucial for project success.
upvoted 0 times
...
Keva
10 months ago
A) Relationship between the planned and actual cost
upvoted 0 times
...
...
Lilli
11 months ago
I'm going with B) Difference between the planned benefit and budgeted cost. That's a key metric for any project, isn't it? The CPI can help us stay on top of it.
upvoted 0 times
Melda
10 months ago
I agree, both A) Relationship between the planned and actual cost and B) Difference between the planned benefit and budgeted cost are key metrics to track in project management.
upvoted 0 times
...
Vallie
10 months ago
I think A) Relationship between the planned and actual cost is also important to monitor to ensure the project stays on track.
upvoted 0 times
...
Sabrina
10 months ago
Yes, you're right. Keeping track of the planned benefit versus the budgeted cost is crucial for project success.
upvoted 0 times
...
...
Bernardo
11 months ago
A) Relationship between the planned and actual cost. That's what the CPI tracks, right? Workfront makes it easy to keep an eye on those numbers.
upvoted 0 times
Myra
10 months ago
I agree, having that visibility into the planned versus actual cost is crucial for project success.
upvoted 0 times
...
Jeannetta
10 months ago
Workfront definitely helps with keeping track of those numbers and making sure everything is on track.
upvoted 0 times
...
Avery
11 months ago
It's important to monitor the CPI to ensure the project stays on budget.
upvoted 0 times
...
Natalie
11 months ago
Yes, that's correct. The Cost Performance Index tracks the relationship between the planned and actual cost.
upvoted 0 times
...
...