Refer to the exhibit.
Tyson has a capacity of 7 hours per day.
What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)
To ensure Tyson is not over-allocated in the Workload Balancer, a system administrator can take the following actions:
Edit Task Allocation: The administrator can adjust the allocation of hours for the 'Verify Intake Form' task. Specifically, they can redistribute the hours from Wednesday (where Tyson is over-allocated with 9 hours) to other days where Tyson has available capacity.
Reassign Task: The administrator can reassign the 'Kickoff Meeting' task to another user who has available capacity. This will immediately reduce Tyson's workload and ensure the task is still completed without overburdening Tyson.
Reference
Workfront documentation on using the Workload Balancer highlights these options for managing user allocations and ensuring workloads are balanced across team members.
Jovita
25 days agoRaymon
26 days agoShawn
4 days agoHildred
14 days agoHelaine
18 days agoFelicia
1 months agoDarrin
10 days agoTu
16 days agoLeah
18 days agoEzekiel
2 months agoGilma
2 months agoSanjuana
11 days agoSkye
1 months agoBarrett
1 months agoCarman
1 months agoShawnee
2 months agoMozell
2 months agoTamekia
2 months agoRuth
19 days agoCaitlin
25 days agoAleta
26 days agoBok
1 months agoShonda
1 months ago