Adobe Exam AD0-E903 Topic 3 Question 21 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 21
Topic #: 3
[All AD0-E903 Questions]

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, creating a custom status specifically for 'Backlog' allows the team to differentiate between work that is pending capacity and work that is actively being planned. This prevents confusion and allows for better project tracking, ensuring that tasks move smoothly from backlog to the planning phase when appropriate.


Contribute your Thoughts:

Frederica
1 days ago
I think option C is the way to go. Having a dedicated Backlog status will make it crystal clear which projects are just sitting in the queue versus ones that are actively being planned.
upvoted 0 times
...
Dianne
5 days ago
I agree with Casie, it will help differentiate between backlog and planning.
upvoted 0 times
...
Casie
7 days ago
I think we should create a custom status for Backlog.
upvoted 0 times
...