Actual exam question for AACE International's Planning & Scheduling Professional (PSP) Exam exam
Question #: 9
Topic #: 3
[All Planning & Scheduling Professional (PSP) Exam Questions]

If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Tawna
1 days ago
I believe it will be -14 calendar days due to the delays described.
upvoted 0 times
...
Celestina
2 days ago
I think the total float calculation will be 0 calendar days.
upvoted 0 times
...
Eve
13 days ago
D) 10 calendar days.
upvoted 0 times
...
Twila
14 days ago
C) -20 calendar days.
upvoted 0 times
...
Lou
15 days ago
B) -14 calendar days.
upvoted 0 times
...
Isadora
16 days ago
A) 0 calendar days.
upvoted 0 times
...
Kimbery
17 days ago
What will the total float calculation be at the end of the project?
upvoted 0 times
...