Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 1 Question 18 Discussion

Actual exam question for AACE International's CCP exam
Question #: 18
Topic #: 1
[All CCP Questions]

In a fixed price contract the:

Show Suggested Answer Hide Answer
Suggested Answer: C

In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.

Top of Form

Bottom of Form


Contribute your Thoughts:

Devorah
26 days ago
Well, at least the contractor won't have to worry about going over budget. That's a silver lining, right?
upvoted 0 times
Alexia
16 days ago
A) Contractor has no risk in the project
upvoted 0 times
...
...
Kiley
28 days ago
C? Really? That's just plain wrong. In a fixed price contract, the contractor is paid a set amount, not actual costs.
upvoted 0 times
...
Pok
30 days ago
D seems a bit too extreme. The owner has some risk, but not all of it. I'm going with B.
upvoted 0 times
Mattie
19 hours ago
Yeah, B seems like the most balanced choice. The contractor should have some risk in the project.
upvoted 0 times
...
Christiane
2 days ago
I think B is the best option too. It's important for the contractor to have some stake in the project.
upvoted 0 times
...
Lorrie
12 days ago
I agree, B makes more sense. The contractor should assume some performance risk.
upvoted 0 times
...
...
Allene
1 months ago
I was going to choose A, but I guess that wouldn't make much sense since the contractor is the one taking on the risk.
upvoted 0 times
Lashaun
3 days ago
That's correct, the contractor takes on the risk in a fixed price contract.
upvoted 0 times
...
Noel
4 days ago
B) Contactor assumes all the performance risk
upvoted 0 times
...
...
Audria
2 months ago
I think B is the correct answer. In a fixed price contract, the contractor assumes all the performance risk.
upvoted 0 times
Barrett
19 days ago
Yes, the contractor bears all the performance risk in a fixed price contract.
upvoted 0 times
...
Jeannetta
1 months ago
That's correct, the contractor takes on the risk in a fixed price contract.
upvoted 0 times
...
Yun
1 months ago
I agree, in a fixed price contract the contractor assumes all the performance risk.
upvoted 0 times
...
...
Celeste
2 months ago
I'm not sure about that. I think the answer might be C) Contractor is paid for actual costs.
upvoted 0 times
...
Maxima
2 months ago
I agree with Alex. In a fixed price contract, the contractor takes on the risk of completing the project within budget.
upvoted 0 times
...
Alex
2 months ago
I think the answer is B) Contractor assumes all the performance risk.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77