In a fixed price contract the:
In a fixed-price/lump-sum contract, the agreed price is fixed and generally not subject to adjustment based on fluctuations in costs, unless explicitly stated in the contract terms. Payment for adjustments in construction costs due to fluctuations in resource prices or delays is typically not allowed unless there is a specific provision for such adjustments, which is rare in fixed-price contracts. Therefore, the correct answer is C. In no situation.
Top of Form
Bottom of Form
Devorah
26 days agoAlexia
16 days agoKiley
28 days agoPok
30 days agoMattie
19 hours agoChristiane
2 days agoLorrie
12 days agoAllene
1 months agoLashaun
3 days agoNoel
4 days agoAudria
2 months agoBarrett
19 days agoJeannetta
1 months agoYun
1 months agoCeleste
2 months agoMaxima
2 months agoAlex
2 months ago