AACE International Exam AACE-PSP Topic 3 Question 16 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 16
Topic #: 3
[All AACE-PSP Questions]

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Yuonne
2 days ago
Wait, what? 9001 and 6002 and 6002? That's like a triple-decker sandwich of activities. I'll have to pass on that one. B) 1000, 1001, and 6001 seems more reasonable.
upvoted 0 times
...
Graciela
5 days ago
Hmm, let's see. The change order impacted Activity 6001, so that's a given. But what about the other activities? Looks like D) 1000 and 6001 is the way to go. Simple and straightforward.
upvoted 0 times
...
Daren
10 days ago
I'm not sure. I think it could also be D) 1000 and 6001.
upvoted 0 times
...
Stanton
12 days ago
I agree with Kizzy. The scope change would impact those activities.
upvoted 0 times
...
Kizzy
13 days ago
I think the answer is B) 1000, 1001, and 6001.
upvoted 0 times
...
Laila
15 days ago
I'm not sure about the answer. Can someone explain the rationale behind it?
upvoted 0 times
...
Sherly
19 days ago
I agree with Pete. The scope change would impact those activities.
upvoted 0 times
...
Pete
21 days ago
I think the answer is B) 1000, 1001, and 6001.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77