AACE International Exam AACE-PSP Topic 1 Question 14 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 14
Topic #: 1
[All AACE-PSP Questions]

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Maxima
12 days ago
I'm not sure, but I think the finish date might be 09 Sep 2021.
upvoted 0 times
...
Paulina
13 days ago
I disagree, I believe the finish date would be 08 Sep 2021.
upvoted 0 times
...
Victor
17 days ago
Hmm, let's see. If we start Activity 2002 on 12 August 2021, I think the finish date would be 09 Sep 2021. Option C looks like the right answer.
upvoted 0 times
...
Kassandra
20 days ago
I think the finish date for Activity 2002 would be 19 Sep 2021.
upvoted 0 times
...